Kitchens planned down to the drawer.

From a refresh that keeps your layout to a full rebuild with a wall removed: what's included, what it usually costs here, and how many weeks you'll be without a sink.

Kitchen with charcoal shaker cabinets, white subway tile, open oak shelves over the sink and a pale wood floor
Fig. 01An example of the kind of kitchen we build. Photo is illustrative.
Included

What every kitchen includes

Whatever the size, the same things happen in the same order. Nothing on this list is an extra.

  • DesignMeasured drawings, plan and elevations, two rounds of revisions, selections with our designer.
  • PermitsA building permit pulled where the work needs one: moving walls, plumbing or venting.
  • ProtectionDust walls, floor protection, daily cleanup and disposal.
  • Rough-inPlumbing, wiring and venting by our regular trades, inspected before walls close.
  • Walls and ceilingsInsulation where open, drywall, primer and two coats of paint.
  • CabinetryInstalled, levelled and adjusted, hardware included.
  • Counters and backsplashTemplated once the cabinets are set, so they fit what was built.
  • LightingPot lights, under-cabinet lights and pendants as drawn.
  • FlooringNew, or patched to match where cabinets moved.
  • WalkthroughA written deficiency list, closed before the final invoice.
Price ranges

What kitchens cost in Waterloo Region

Most kitchens land in one of these three ranges. They include design, permits, materials and labour, before HST.

Kitchen price ranges for 2026, with typical time on site.
Type of jobWhat it usually meansTypical priceOn site
RefreshSame layout. New cabinets or doors, counters, sink, backsplash and lighting. Appliances kept.$28,000 to $45,0003 to 5 weeks
Full remodelSame footprint, everything new, wiring and plumbing brought up to code where walls are open.$55,000 to $90,0006 to 9 weeks
New layoutSink or range moved, an island added, often a wall opened with an engineered beam.$85,000 to $140,0008 to 11 weeks
Timeline

A full remodel, week by week

This is the usual shape of a nine-week job. Yours comes with real dates, and you sign it before demolition. Terracotta bars are waits we don't control: the city inspection and the counter fabricator.

Stage
Protection and demolitionWeek 1
Plumbing, electrical, venting rough-inWeek 2
City inspectionWeek 3, a wait we don't control
Insulation, drywall, paintWeeks 3 to 4
Flooring and cabinet installWeek 5
Counter template and fabricationWeeks 6 to 7, at the fabricator
Counters, sink, backsplashWeek 8
Trim, appliances, final inspection, walkthroughWeek 9

Cabinets usually take six to ten weeks to make. We order them when you sign and they are in our shop before demolition, so that wait happens while you still have a kitchen.

What moves the price

Six things that decide where you land

Cabinet construction
Stock boxes with custom doors, semi-custom, or fully custom. The biggest single line on most kitchen quotes.
Moving the sink or range
New drain routes and gas lines mean opening floors and a permit. Leaving them where they are saves real money.
Walls
A load-bearing wall adds an engineer, a beam and posts, and usually $12,000 or more.
Counter material
Quartz sits in the middle. Quartzite, marble and large porcelain slabs cost more to buy and to fabricate.
Venting
A hood ducted out through a brick wall costs more than one run through a nearby joist bay.
Old wiring
Knob-and-tube or a full panel has to be dealt with before a new kitchen can be powered.